PROJECT SPOTLIGHT

Project: Plunketts Pest Control Warehouse Expansion

Project Manager: Mike Heinze

Kraft Field Superintendents: Matt Penttila – Sheetmetal, Mitch Hackl – Pipe Fitter, Joe Hutton – Plumber

Location: Fridley, MN

Final Construction Cost: $108,500

General Contractor: Westin Construction

Architect/Engineer: Kraft (Design Build)

Date Completed: January 2023

PROJECT SCOPE:

Kraft Provided design build mechanical and plumbing services for Plunkett’s new 14,000 SQFT warehouse addition, work included adding additional plumbing fixtures, floor drains and roof drains. Kraft provided unit heaters and infrared heating as well as an intake and exhaust for the warehouse CO/NO system. Kraft worked with Xcel Energy to facilitate upgrading the existing gas meter to handle the expanded heating load as well as the installation of over 500’ of new gas piping.