PROJECT SPOTLIGHT

Project: South St. Paul Community Learning Center

Project Manager: Mike Heinze

Kraft Field Superintendents: Jeff Bagwill – Pipefitter, Eric Holter – Sheetmetal, Ben Longfellow Plumbing

Location: South St. Paul, MN

Final Construction Cost: $243,000

General Contractor: Kraft Mechanical

Architect/Engineer: World

Date Completed: September 2022

PROJECT SCOPE:

Kraft Replaced (1) existing Boiler with (2) 1,000,000 BTU Riello Boilers and upgraded the existing domestic water heater to a indirect heating system utilizing a heat exchanger and hot water storage tank served by the new boilers. Kraft provided alternative CPVC breeching as a value engineering option for the project which saved the facility $5000 on the project cost.