PROJECT SPOTLIGHT
Project: South St. Paul Community Learning Center
Project Manager: Mike Heinze
Kraft Field Superintendents: Jeff Bagwill – Pipefitter, Eric Holter – Sheetmetal, Ben Longfellow Plumbing
Location: South St. Paul, MN
Final Construction Cost: $243,000
General Contractor: Kraft Mechanical
Architect/Engineer: World
Date Completed: September 2022
PROJECT SCOPE:
Kraft Replaced (1) existing Boiler with (2) 1,000,000 BTU Riello Boilers and upgraded the existing domestic water heater to a indirect heating system utilizing a heat exchanger and hot water storage tank served by the new boilers. Kraft provided alternative CPVC breeching as a value engineering option for the project which saved the facility $5000 on the project cost.